Offloaded topside equipment for Nexans Aurora

During some hectic days, a total of 197 heaves of topside equipment for the cable laying ship Nexans Aurora have been offloaded at Ulstein Verft. The largest single heave was the cable capstan with a net weight of 176 tonnes.

LES PÅ NORSK

The cable lying vessel Nexans Aurora is a large and compact ship. Measuring 149.9 metres in length and 31 metres in width, she has a dead weight of 17,000 tonnes. She has been designed to handle large quantities of subsea cables.
 

On 15 June, the hull of the Nexans Aurora arrived at Ulstein Verft. A few days later, a cargo vessel arrived at the shipyard, carrying several hundred tonnes of topside equipment to be installed in the cable laying vessel. The heavy lift department at Ulstein Verft operates a mobile crane which is capable of lifting 600 tonnes, so the heave of the 176t capstan from Maats Tech Ltd offered no difficulties.

Maats utstyr Nexans Aurora 11

In total, three ship loads of topside equipment will be delivered and unloaded at Ulstein Verft in connection with this project. In addition comes all the other truck deliveries. In the next ship delivery the cable carousel will arrive. This has a capacity of 10,000 tonnes and can handle two cables at the same time. Normal cable diameter will be approximately 20 centimetres.

Included in the many other heaves were the two large lay wheels and all the 264 rollers for the cable carousel.

Lifting of Maats equipment package for the CLV vessel Nexans Aurora.

The hull of the Nexans Aurora has now been positioned in the dock hall at Ulstein Verft, and the outfitting of this newbuild has started.
 

The heavylift department are on their way to new assignments, this time at Fosen Yard in Rissa, county of Trøndelag, to transport a 130-tonne engine room section. For this task, two Goldhofer multiwheelers will be used, which have a total transport capacity of 640 tonnes.

Latest news

X CONNECT GUI PMS
Press Release

Introducing ULSTEIN® POWER VSG: Setting new standards in marine power efficiency

The ULSTEIN® POWER Variable Speed Generator (VSG) has been designed to optimise power generation on marine vessels by dynamically adjusting its speed to match load requirements. Together with technical measures and overall ship design, the operational results on the CSOV Olympic Boreas show a record-low 2.7-tonne fuel consumption per 24 hours during a week of DP operations. 

A birds view on Olympic Notos 20241005 Olympic Notos OCLIN 19 MARTIN GISKEGJERDE
Feature

Big fuel savings on first CSOV newbuilds with Ulstein’s TWIN X-STERN® concept

Taking bold commercial risks on novel vessel concepts with a strong focus on sustainability has made Olympic a pioneering player in the offshore energy sector. Its latest investment in a pair of new-build Construction Service Operation Vessels (CSOVs) based on Ulstein Group’s innovative TWIN X-STERN® solution has paid off, with close to 50% reductions in fuel consumption and emissions to boost environmental performance.

20241005 Olympic Notos OCLIN 11 MARTIN GISKEGJERDE
Press Release

Ulstein delivers CSOV vessel Olympic Notos to Olympic

13 November 2024: Ulstein is proud to announce the successful delivery of the Construction Service Operation Vessel (CSOV) Olympic Notos to Olympic. This state-of-the-art vessel marks a significant milestone in maritime innovation and excellence. “As a result of the findings from her sister ship, Olympic Boreas, the shipping company states that the vessels "operate with close to a 50% reduction in fuel consumption compared to other sailing CSOVs."

DSC4731 comp bw

Jostein Sørnes

Section leader Heavy Lift/NDT operator

Affiliation
Ulstein Verft AS