High activity on 'Nexans Aurora' shipbuilding project

The construction of the next-generation cable laying vessel, the 'Nexans Aurora', is well underway at Ulstein Verft. In such a complex newbuild project, several tasks are carried out at the same time. On 10 September 2020, the cable capstan was installed during a short break in the ongoing paint process.

  • Early morning 11 September 2020: Nexans Aurora bow part.
  • Afternoon 10 September 2020: Nexans Aurora bow part.
  • Preparing for the capstan lift.
  • The Demag CC2800-1 mobile crane performing the capstan lift.
  • The cable capstan installed.

Les på norsk

During a time span of a few days in September 2020, the cable capstan has been installed, the paint process is ongoing and the thrusters are about to be installed.

With a length of 149.9m, a beam of 31m and a dead weight of 17,000t, the 'Nexans Aurora' is one of the largest vessels being constructed in the history of Ulstein Verft. With a large 10 000t capacity and split turntable, the vessel is well prepared for complex construction tasks in severe weather conditions anywhere in the world. Her first assignment will be to install the export cables for the Seagreen offshore wind farm project. The construction on the 1,075 megawatt (MW) project will start in 2021. When completed, the Seagreen 1 will be Scotland's largest wind farm.
 

Latest news

IMG 9692
Feature

How Ulstein tested a new cable-laying vessel design

How can you be confident that a new vessel design will actually perform in rough seas and demanding operations? The answer lies in thorough verification, independent testing and documented performance. Recently, a new Ulstein design for a cable-laying vessel was tested in a large-scale ocean basin at SINTEF Ocean. The results delivered exactly what Ulstein seeks: confidence that the design performs as intended.