Nexans' cable-lay vessel newbuilds
Nexans Electra is a state-of-the-art cable-laying vessel from Ulstein Verft, to be delivered in 2026. Follow the progress here. The ship is an updated version of the Nexans Aurora, a 2021 delivery.
Nexans: Electrifying the future
The DP3 sister vessels for Nexans are 149.9 m long and 31 m wide and developed for work in the offshore renewables market, installing subsea cables, including cables connecting offshore wind farms to the grid and interconnector systems. Operational tasks include power cable and umbilical laying, bundle laying, cable jointing and repair, cable system protection and trenching.
Sister vessels
Nexans Electra
The cutting-edge cable laying vessel features a split turntable on deck capable of holding up to 10,000t of cable, an under-deck turntable with a 3,500t cable capacity, and a fibre optic basket holding 450t. The vessel measures 31 metres in width, 149.9 metres in length, and is accommodated for a crew of 90.
Stories
Milestone celebration for advancing cable installation
Nexans' next state-of-the-art cable installation, the 'Nexans Electra' is another step closer to realisation. The grand block ceremony was celebrated on 10 September 2024 at CRIST, Poland. The vessel will be finalised at Ulstein Verft, Norway.
Keel laying ceremony for the CLV vessel Nexans Electra
On 4 April 2024, the keel laying ceremony took place for the DP3 cable laying vessel (CLV) Nexans Electra. This vessel will transport and lay various types of subsea cables, including cable bundles, as well as handle recovery and repair operations for Nexans Marine Operations AS in Norway.
Successful first steel cutting for Nexans’ next CLV
On 19 January 2024, on the day four months after signing the shipbuilding contract, Nexans Marine Operations AS and Ulstein Verft could celebrate the start of the construction of Nexans’ next cable laying vessel. Attending the steel cutting ceremony at the Crist hull yard were representatives from Nexans, Ulstein Verft, DNV and Crist.
Ulstein Verft signs new shipbuilding contract
On 19 September 2023, Nexans Marine Operations AS and Ulstein Verft entered into a contract on the construction of a large DP3 cable laying vessel.
'Nexans Aurora'
The advanced cable laying vessel has a turntable with a large cable capacity of 10,000 tonnes, and the fibre optic basket holds 450 tonnes. The vessel is 31 m wide, 149.9 m long, and has a deadweight of 17,000 tonnes. Accommodation for 90 people.
Stories
Three keys to a successful on-time vessel delivery
On-time delivery is often underestimated when evaluating vessel newbuilding projects. Delayed deliveries can represent an additional cost that can be as high as the original, newbuilt price of the vessel. The Norway-based shipyard, Ulstein Verft, is reputed for its precise deliveries. What do they do to achieve this?
Both newbuilds nominated 'Ship of the Year'
Both the newbuilds at Ulstein Verft are nominees for the ‘Ship of the Year 2021’ Award; the polar vessel 'National Geographic Resolution' and the cable-laying vessel 'Nexans Aurora'. The ‘Ship of the Year’ is awarded by the maritime magazine Skipsrevyen and the winner will be announced in August.
Naming the cable laying vessel ’Nexans Aurora’
The DP3 Cable Laying Vessel, Nexans Aurora’, was named at Ulstein Verft on 8 June 2021. The lady sponsor is Mrs Anne Lise Aukner, former Managing Director of Nexans Norway.
Delivery of the CLV vessel ’Nexans Aurora’
The final milestone of the Aurora construction adventure was reached today, on 31 May 2021, when the DP3 Cable Lay Vessel ‘Nexans Aurora’, the state-of-the-art flagship of the Nexans fleet, was delivered from Ulstein Verft.
A sunny ride on the ‘Nexans Aurora’ sea trial
Snow-covered mountain tops, green hillsides and a bright sun on a blue sky make a perfect frame for the lady in red, the CLV vessel ‘Nexans Aurora’, on her sea trial. A sunny mood also characterizes the atmosphere on board the vessel.
Theory meets real life
In any other year, the shipyard Ulstein Verft is happy to welcome student groups, but Covid-19 set an abrupt halt to group visits. However, the program manager of the Ship Design study at NTNU Ålesund recently came up with a solution.
Completed equipment installations on Nexans Aurora
The construction project of the cable lay vessel 'Nexans Aurora' has recently reached a new milestone, as the installation of the MAATS Tech equipment package including the carousel, loading arms, access tower and control cabin have now been completed.
Quality at all levels - installing the IAS system on the Nexans Aurora
“Quality at all levels”, says Per Jarle Ytrebø at Ulstein Elektro Installasjon when explaining why they are well positioned with the setup of the IAS system (Integrated Automation System) on the cable lay vessel Nexans Aurora, currently under construction at Ulstein Verft.
Steady progress on Nexans Aurora
12 February 2021: During the past few days of the shipbuilding project of the CLV Nexans Aurora, the outer part of the carousel has been mounted. Currently we are installing the fairings.
The A-frame in position on the ‘Nexans Aurora’
On 29 January 2021, the large, 150-tonne, A-frame for the DP3 cable laying vessel ‘Nexans Aurora’, under construction at Ulstein Verft, was lifted into position.
Carousel delivery for the CLV 'Nexans Aurora'
During the time span of 2.5 days and after 272 heaves, the carousel equipment for the cable lay vessel Nexans Aurora has been offloaded at Ulstein Verft.
Nexans Aurora on the water
On 8 November 2020, Nexans’ next-generation Cable Laying Vessel, the ‘Nexans Aurora’ was launched at Ulstein Verft. The 149.9 m long and 31 m wide vessel will be working in the offshore renewables market, installing subsea cables including cables connecting offshore wind farms to the grid and interconnector systems.
Installation of cable lay equipment commences on Nexans Aurora
The installation of the state of the art, MAATS cable lay equipment on board the CLV vessel Nexans Aurora has now commenced at the Ulstein Verft shipyard.
Thruster installation completed
In September 2020, the three azimuth propulsion thrusters were installed in the cable-laying vessel 'Nexans Aurora', which is under construction at Ulstein Verft. Each thruster has an effect of 3,200 kW and a diameter of 2,900 mm.
High activity on 'Nexans Aurora' shipbuilding project
The construction of the next-generation cable laying vessel, the 'Nexans Aurora', is well underway at Ulstein Verft. In such a complex newbuild project, several tasks are carried out at the same time. On 10 September 2020, the cable capstan was installed during a short break in the ongoing paint process.
Main equipment being installed
The main equipment for the CLV vessel 'Nexans Aurora' is currently being lifted on board the vessel and mounted. The engine on these photos is the third of six main engines.
Offloaded topside equipment for Nexans Aurora
During some hectic days, a total of 197 heaves of topside equipment for the cable laying ship Nexans Aurora have been offloaded at Ulstein Verft. The largest single heave was the cable capstan with a net weight of 176 tonnes.
Outfitting of the Nexans Aurora starts at Ulstein Verft
In June 2018, a shipbuilding agreement was signed between Nexans and Ulstein on a large, DP3, cable laying vessel (CLV) to support markets such as the offshore wind industry. The construction project now enters a new phase, as the outfitting work at Ulstein Verft is about to start.
All blocks assembled for Nexans Aurora
All the grand blocks for the Cable Laying Vessel (CLV) ‘Nexans Aurora’ have now been assembled at the hull yard, CRIST. Work tasks such as some steel work, outfitting and paint work now need to be carried out before the hull can be towed to Ulstein Verft, Norway, for finalising.
Grand block ceremony for the next step in cable installation
On 15 October 2019, Nexans hosted the grand block ceremony for their new cable installation vessel, the ‘Nexans Aurora’. The vessel will be completed at Ulstein Verft in Norway.
Nexans Aurora - another milestone passed
The keel laying ceremony of the DP3 cable laying vessel 'CLV Nexans Aurora' was held on 24 April 2019. The vessel is destined for the installation of subsea cables by Nexans, a global actor in cabling systems and services.
Major milestone passed for Nexans’ C/S Aurora
The first major milestone in the construction of Nexans’ new DP3 cable laying vessel, the C/S Aurora, was passed Monday 18 February 2019 with the cutting of the first steel.
Ulstein Verft to construct large cable laying vessel for Nexans
Nexans Subsea Operations has signed a shipbuilding contract with Ulstein Verft on the construction of a large, DP3 cable laying vessel.
Get in touch
Kolbjørn Moldskred
- Description
- Sales Manager Newbuild
- Affiliation
- Ulstein Verft AS
Lars Lühr Olsen
- Description
- Managing Director
- Affiliation
- Ulstein Verft AS